Exterior completed
Looks like all the units have been completed, tying up the details only.
Sunday, February 27, 2011
Removing hoarding
The hoarding are being removed.
Tuesday, January 25, 2011
Perimeter fencing
Putting up the brick walls for the individual perimeter fencing.
Wednesday, November 17, 2010
Roof all done
Now workers are putting in the windows and tiles.
Thursday, October 21, 2010
Only 2 units no roof
The 4 units of semi-dees that are near the guard house and nearer to Jalan Sutera 1 have their roof completed. So now only 2 units left yet to install their roof.
Friday, October 1, 2010
Roof truss
This is the block of 2 units of semi-dees nearest to the shop houses. The roof truss is being installed.
Monday, September 27, 2010
4 still no roof
Only 4 units are left that are not rendered and without roof.
Older Posts
Home
Subscribe to:
Posts (Atom)
Followers
Blog Archive
▼
2011
(3)
▼
May
(1)
Exterior completed
►
February
(1)
►
January
(1)
►
2010
(9)
►
November
(1)
►
October
(2)
►
September
(1)
►
August
(1)
►
June
(1)
►
March
(3)
►
2009
(10)
►
December
(1)
►
October
(1)
►
September
(1)
►
August
(1)
►
July
(1)
►
June
(1)
►
April
(1)
►
January
(3)
►
2008
(1)
►
November
(1)
About Me
Jalil Sutera
View my complete profile